METRO RAIL DESIGN CRITERIA SECTION 9 / SYSTEMS
Appendix B
DE304.09 Appendix 9B-1 Revision 1 : 05/09/12
Metro Baseline Re-Baseline: 04/20/10
1 SCADA RTU Interface Requirements
This section describes the interface requirements between the SCADA RTU subsystem and
external equipment.
1.1 General Interface Requirements
The SCADA RTU shall be the gateway for all indication and control interfaces to ROC. Data
acquisition shall be implemented using a combination of in-rack I/O modules, distributed remote
I/O and local subsystem communications links.
Interlocks shall be implemented in subsystem controls to prevent unsafe or destructive remote
operation of equipment.
Interlocks shall be implemented in the field device control circuits and shall not be implemented
in PLC logic except where approved by Metro.
1.2 Discrete Indications
Each indication from external subsystems and equipment shall be in the form of an isolated dry
contact rated at no less than 200VDC at 2 amperes.
One unshielded twisted wire pair between the subsystem control circuit and the SCADA PLC
CIC or MDF shall be provided for each discrete indication.
The SCADA RTU shall provide 24VDC class-B wetting voltage current limited to 2 amperes on
one wire in the pair and sense the return on the other wire. Indications shall function properly
regardless of polarity; however, polarity shall be consistently wired system-wide.
Unless otherwise specified or approved by Metro, all indicating relays shall be normally de-
energized.
Unless otherwise specified or approved by Metro, all indications shall utilize the relay normally
open contact.
Unsupervised indication relays for fire life safety and security functions shall be normally
energized.
1.3 Discrete Controls
Unless otherwise specified or approved by Metro, all discrete controls shall be a momentary dry
contact closures.
One unshielded wire pair shall be provided for each discrete control.
Control voltage shall be limited to 48VDC.
Subsystem control circuits shall implement any necessary interposing and seal-in (set) relays
and reset relays so that a reset of the SCADA RTU does not affect the control state of field
equipment.